Tunnel boring machine
startup at entrance portal
Parsons' design team provided an innovative reconfiguration concept for the I-25/I-225 interchange. This design moved light rail trains from the highest level of the interchange to the lowest level resulting in significant cost savings, aesthetic improvements, and improved temporary traffic control.
An important feature of the I-25 reconstruction is the I-25/Mississippi Avenue outfall. Approximately 3,000 feet long, the outfall conveys stormwater away from the I-25 and Logan bridge intersection. On any given day, heavy rains flood and strand travelers, who have coined the name "Lake Logan" for this area of the interstate. A 12-foot-diameter section of the outfall under Mississippi Avenue, about 800 feet long, was constructed using an earth pressure balance (closed mode) tunnel-boring machine. Parsons' design alternative reduced the length of the alignment by one third— avoiding costly right-of-way acquisitions— and diverted the tunnel away from potentially hazardous materials along the original route.
Parsons was the primary designer of 19 miles of double-track light rail transit along I-25 and I-225 including 13 new transit stations, park-and-ride lots, three new parking garages, a new operations control center, power and signal systems, and a supervisory control and data acquisitions system for the existing transit lines. These highway and transit improvements bring long-term transportation relief for some of metro-Denver’s fastest-growing and most congested areas.
T-REX included more than $60 million in intelligent transportation system (ITS) elements. Parsons was the primary designer of the ITS, including dynamic message signs; CCTV cameras; freeway and arterial detection (to monitor surface street congestion); ramp metering; a communications network; an Interim Traffic Management Center housing an incident information management system; and public information Web channels. During the construction phase, a project web site, www.trexproject.com, informed the public of real-time traffic conditions.
Completed I-25/I-225 corridor
By the end of 2002, design for T-REX was 85 percent complete and construction was 25 percent complete. Construction of the light rail line began in Spring 2003. And by Fall 2006, the T-REX project concluded - nearly two years earlier than was requested by the client.