One of Augusta's Most Extensive Utilities Expansions
The Augusta Utilities Department (AUD) in Georgia operates the Highland Avenue Water Treatment Plant (HAWTP) in order to supply drinking water to its customers. Water is pumped from the Savannah River to the holding basins at the HAWTP, which then treats and distributes the water to AUD’s customers. The plant, located at Highland and Central Avenues, was initially constructed in 1899 and subsequently expanded or improved in 1937, 1952, 1964, 1972, 1984, and 1999. In 2004, the city of Augusta decided to expand the plant’s capacity to ensure that the AUD can meet the needs of Augusta's growing population by being able to treat 60 million gallons per day (MGD) of water consistently.
The HAWTP had relied on 10 dual-media, two-celled Leopold filters to treat surface water pumped from the Savannah River into two raw water holding basins (reservoirs) located at the HAWTP. AUD has owned and operated the HAWTP since 1899. As of its last expansion in 1999, the plant was permitted to treat 60 MGD; currently, the HAWTP can produce a continuous 45 MGD, but it can treat up to 60 MGD only for short periods of high demand.
Parsons was hired as the CM-at-risk contractor to modify and upgrade the plant and to increase the sustained operational capacity to its 60 MGD potential. This expansion and its modifications will ensure HAWTP’s sustained operational capacity of 60 MGD.
Aerial view of site. Filter building and Fort Gordon pump
station have white roofs.
Key Features and Objectives
The HAWTP project’s notable features involve water supply and treatment, reservoirs, piping, pumping stations, and disinfection. As CM-at-risk contractor, Parsons’ efforts on the HAWTP include project management, full CM and contracting, value engineering/independent project analysis, cost estimating, final design support and coordination, building trades contracting and coordination, CM and inspection, facility startup and assistance with initial operation, constructibility reviews, permit assistance, website development, and owner-furnished equipment procurement support.
The key issues and challenges included:
- Limited site availability for construction operations
- Safety issues on specific activities and site restrictions
- Community interfaces, including traffic, noise, and dust
- Proximity to airport (security and construction height restrictions)
Parsons undertook a programmatic approach to this project with specific emphasis on the objectives and challenges of Augusta. We worked directly with the city to identify the following key objectives:
- Continuous plant operation throughout work
- Maximum value in implementing improvements within bond funds
- Community acceptance and minimum adverse impacts
- Local involvement and economic opportunity