Client:
Cobb County Water System
Construction Value:
$113.6 million
Project Duration:
September 1999–December 2004
Project Manager:
Darby Clay
Construction Manager:
Dave Rendini
Parsons Services:
Preconstruction constructability and biddability
reviews, construction management,
dispute and claims management, quality assurance and testing, public outreach,
periodic survey checks, full-time observation and inspection, review of
the contractor’s
safety plan, environmental monitoring, and additional services
as required
|
Like many growing metropolitan areas, Cobb County, Georgia
must increase the capacity of its wastewater conveyance system in order
to meet future capacity requirements. The Little Nancy Creek, Sewell Mill
Creek, Sope Creek, Rottenwood Creek, and Chattahoochee sewer interceptors
(ranging from 24 to 72 inches in diameter) serve the eastern portion of
Cobb County, gathering wastewater flows and conveying them to the R.L.
Sutton Water Reclamation Facility. The Chattahoochee interceptor, which
is the largest interceptor, has a capacity of approximately 100 million
gallons per day and runs near capacity at peak flows. Additional conveyance
infrastructure is needed to accommodate future peak hour flows, which
are forecasted to be 300 million gallons by the year 2040.
After evaluating several alternatives, the Cobb County Water
System chose to construct the Chattahoochee Tunnel. A deep tunnel causes
significantly less community and environmental disturbance than traditional,
open-cut sewer lines. The Chattahoochee Tunnel takes a 9.5-mile-long direct
path, an option logistically more attractive than the conventional method,
which would involve installing over 15 miles of sewer lines parallel to
the existing lines. The tunnel is designed to meet east Cobb’s long-term
wastewater capacity needs and to provide flow equalization to the county’s
R.L. Sutton Water Reclamation Facility.


Chattahoochee Tunnel profile.
Cobb County chose Parsons and its subcontractor, Jacobs
Associates (JA), to provide construction management on the largest project
the Cobb County Water System had ever undertaken at the time. Parsons
began work on the Chattahoochee Tunnel project in September 1999, and
construction began in June 2000.
Parsons’ services include preconstruction constructability
and biddability reviews of the 70% contract documents, construction management,
dispute and claims management, quality assurance and testing, public outreach,
periodic survey checks, full-time observation and inspection, review of
the contractor’s safety plan for compliance with the project safety
plan (which was developed under an Owner Controlled Insurance Program),
environmental monitoring, and any additional services the client requests.
|
|
Left: Top view of
the 100-foot-diameter pump station shaft under construction.
Right: Inside view of 16-foot-diameter steel forms used to cast
concrete tunnel liner in place. |
The Chattahoochee Tunnel’s principal elements are:
-
Approximately 49,600 linear feet of hard rock
tunnel, most of which—48,300 linear feet—was excavated using
two high-power tunnel boring machines (TBMs). The rest of the tunnel
was excavated using drill and blast techniques. Each TBM used 39, 19-inch-diameter
cutter disks with 70,000 pounds of thrust exerted on each cutter. It
took seven 422-hp electric motors to drive the 18-foot 4-inch diameter
cutter head on each TBM. The tunnel slopes at a 0.1% grade and varies
in depth with the surface contours from 110 to 350 feet below the surface.
-
Over 1 million tons of cuttings were removed from the
tunnel via horizontal and vertical conveyor belts. The tunnel is partially
lined with approximately 35,000 linear feet of 1-foot-thick concrete
liner, which is currently being installed.
-
A 100-foot-diameter pump station shaft and two 34-foot-diameter
construction shafts were sunk to depths ranging from 180 to 230 feet
using concrete diaphragm walls socketed into rock to support the overburden
section. Pre-excavation grouting of the transition zones and rock
was performed to limit groundwater inflows. The rock sections were
then excavated using drill and blast techniques and supported by rock
bolts, shotcrete, concrete, and similar methods.
-
The four tunnel intakes constructed include surface
structures to intercept flows from existing sewers and drop the flows
through shafts to underground chambers connected to the tunnel. Three
drop shafts and three vent shafts were excavated using raise bore
methods. Ductile iron pipe was installed in these shafts and the annular
space was backfilled with concrete. The drop shafts include tangential
vortex inducers to maximize flow capacity.
|
|
Left: One of two
Robbins tunnel boring machines assembled at the factory.
Right: View from top of construction shaft looking down on tunnel
boring machines being assembled. |
Accomplishments:
-
As part of its public outreach and community involvement
program, Parsons personnel visited each resident immediately adjacent
to the tunnel alignment to discuss what to expect as the TBM passed.
This one-on-one attention was well received and succeeded in minimizing
complaints.


After driving 22,000 feet, the tunnel
boring machine breaks through into the Circle 75 shaft.
Left to right: Ted DePooter (JA), Fred Estep (Parsons), Denver
Chandler (Parsons), Mark Tilly (JA), David Rendini (Parsons),
John Geyer (Parsons), Dwayne Easterling (JA).
|
-
Parsons performed seismograph monitoring of vibrations
along the length of the alignment while the tunnel was being excavated.
Backed up by pre-excavation surveys of structures, the seismic records
provide a means to evaluate any damage claims by residents.
-
Numerous comments during the preconstruction constructability
and biddability reviews helped refine the project documents to obtain
the best pricing among competitive bids.
-
Parsons worked with the design engineer, owner, and
contractor to revise rock bolt requirements, thus saving $500,000.
Parsons is working with these same people to develop a secondary grouting
program that will minimize impacts from groundwater inflows in the
most cost-efficient manner.
While a project’s success is typically measured at
its completion, the ability to achieve that success is present each working
day. Parsons used its considerable experience in construction management
of large underground projects to identify problems at the earliest stage,
resolve problems in a time effective manner at the lowest level, and mitigate
impacts to this immense project. The project is scheduled to be completed
in December of 2004 within the original project budget.
For more information, visit the project
website: www.chattahoocheetunnel.com
Back
|